Red brick residence with a columned oak entrance, granite steps, divided-light windows and an amber maple above a compact autumn garden.

Green Line C Branch Brookline Station Changes: What Riders Need to Know

Green Line trains stop running on Beacon Street this Saturday, Nov. 7. During the shutdown, crews at Fairbanks Street will tear down a platform that will not be rebuilt. When C-branch service returns, Brookline will have fewer stops than it started the year with. Several of the platforms that remain will sit on a different side of their intersection than riders are used to.

The project's goal is accessibility. Where a stop ends up depends largely on its stretch of Beacon Street. Hills at Dean Road and St. Paul Street pushed platforms across their intersections. Fairbanks and Brandon Hall were split across road crossings on a hillside, so they are becoming one stop. Kent Street sits close to its neighbors and carries few riders, so it closes. Elsewhere, the placement of trees and parking spaces shaped the final design.

Why split and closely spaced stops had to change

The MBTA's Green Line C Branch Station Accessibility Improvements project raises platforms eight inches above the rail so riders can step straight into the train. It also adds sloped walkways, widens and levels the platforms, and puts in lighting, benches, shelters and new signs. Other MBTA materials list longer platforms, customer-assistance areas, drainage and emergency-power upgrades, and landscaping.

Rebuilding a platform to these standards is harder when the old stop straddles an intersection or sits on a slope. At a January 2025 community meeting covered by Brookline.News, Mark Shamon, design manager of the Green Line Transformation Program, explained the problem at Fairbanks and Brandon Hall. Both stations are split across road crossings. If each got its own accessible platform in its current spot, he said, "they'd be about 100 feet apart."

Kent Street had the same problem in a different form. It sits less than 800 feet from both Hawes Street and St. Paul Street. Once all three platforms were lengthened and widened, they would be too close together, and stops that close keep trains from reaching full speed. A later Brookline.News report also cited Kent's low ridership.

Stop by stop, the street explains the change

The project covers seven upgraded stations along Beacon Street. Kent Street closes. Washington Square, Coolidge Corner and Saint Mary's Street already met accessibility standards and are not long-term work sites.

Stop What changes What drove it
Englewood Avenue New platforms Accessibility rebuild
Dean Road Outbound platform moves west, onto the same side as inbound The hill east of Dean Road is too steep for an accessible path
Tappan Street New platforms Accessibility rebuild
Fairbanks Street and Brandon Hall Combined into one stop, slightly west of today's Brandon Hall Split crossings and a hillside where westbound Beacon sits about 10 feet above the tracks
Summit Avenue Platforms move between Marion Street and Summit Avenue Placed to protect trees and parking
St. Paul Street Inbound platform moves to the east side of the intersection Steep hill on the west side
Kent Street Closes Less than 800 feet from Hawes and St. Paul; low ridership
Hawes Street Platforms widened; the eastbound U-turn lane closes Widening chosen over staggered platforms to save parking and two large trees

Several stations will also have their inbound and outbound platforms on the same side of the intersection. The MBTA says the change reduces crowding and makes room for wider platforms. For riders, the practical upshot is that the corner where you board may change even at a stop that stays open.

The hillside at Fairbanks and Brandon Hall

Fairbanks and Brandon Hall are less than 700 feet apart on a hillside. People coming from the neighborhoods to the north have always reached them by two public staircases, which lead down from crosswalks across the raised westbound side of Beacon Street.

Brookline.News reported that the new "Fairbanks Street/Brandon Hall" station keeps those stairs and adds an accessible ramp from the westbound platform to a new crosswalk across the raised section of Beacon Street. Sloped walkways with railings and benches will connect all three entrances.

This stop drew the most debate at the January 2025 meeting. Fran Perler, a Town Meeting member who serves on Brookline's Council on Aging, pointed out how hilly that stretch of Beacon Street is. She argued that a longer walk to the combined station would make daily trips harder for riders who depend on the nearest stop. Other attendees agreed with her. Attendees also asked why Kent was chosen for closure instead of Hawes, and why either stop had to go.

Trees were the other concern. The hillside is covered in small oaks, most under six inches wide. According to Brookline.News coverage of a February 2026 Tree Planting Committee meeting, the MBTA chose the combined station's layout to remove as few trees as possible and to save the largest ones on the slope. A short retaining wall behind the platform will catch stormwater and channel it to nearby drains.

Across all the stations, the design removes 96 trees, 50 of them young and 46 mature. The MBTA has committed to planting 98 new ones, each with a one-year maintenance period and warranty before it becomes town property. The replacements will grow in continuous tree lawns behind the platforms instead of in individual pits. The goal is to carry on the tree-lined median that Frederick Law Olmsted and John C. Olmsted designed for Beacon Street in 1886.

What two fewer stops buy in time

With Kent closed and Fairbanks folded into Brandon Hall, the MBTA's environmental analysis forecasts faster trips. It estimates savings of about 31 seconds per passenger on morning peak eastbound trips and about 54 seconds on afternoon peak westbound trips. MBTA project staff later put the improvement at three to seven percent of travel time.

Those seconds go to the people already on the train. Riders who used to board at Fairbanks or Kent will instead walk to a neighboring stop. Near Fairbanks, that walk is on a hill, which is the trade-off the 2025 meeting was about.

Nov. 7 to 15: where the shuttles stop

The shutdown is bigger than Brookline. The MBTA is suspending Green Line service from North Station to Cleveland Circle and the other branch terminals for signal upgrades in the central subway. Brookline's contractor is using the same window to work around the clock in 12-hour shifts. The work includes the Fairbanks demolition, ramp work at Brandon Hall, new inbound platforms at Summit and Hawes, and concrete platform pours at St. Paul.

Shuttle buses run between Cleveland Circle and Copley/Back Bay. The MBTA's C-branch alert lists these Beacon Street stops:

  • Cleveland Circle: Beacon St at Cleveland Circle station
  • Englewood: inbound at Clinton Path, outbound at Englewood Avenue
  • Dean: inbound at Dean Road, outbound at Corey Road
  • Tappan: inbound at Tappan Street, outbound at Williston Road
  • Washington Square: both directions at Washington Street
  • Fairbanks: inbound at Fairbanks Street, outbound at Lancaster Terrace
  • Summit: inbound at Marion Street, outbound at Summit Avenue
  • Coolidge Corner: both directions at Harvard Street
  • St. Paul: both directions at St. Paul Street
  • Hawes: inbound at Hawes Street, outbound opposite Hawes Street

Brandon Hall, Kent Street and Saint Mary's Street have no shuttle stop. The MBTA says trips will take at least 25 minutes longer than usual and that every shuttle bus is accessible. Accessible van service covers Green Line stops between Kenmore and North Station, plus Downtown Crossing. The Framingham/Worcester commuter rail line is free between Lansdowne and South Station, and the Route 39 and Route 57 buses are fare-free. To continue past Back Bay toward North Station, the MBTA directs riders to the Orange Line.

According to the Town of Brookline's calendar, train service is expected back around 2 a.m. on Monday, Nov. 16.

What the map looks like by spring

The Town's Oct. 23 construction update aimed to open new platforms at Englewood, Dean, Tappan and Brandon Hall by Oct. 31. The MBTA lists Tappan's inbound and outbound platforms and Englewood's outbound platform as back in service. The MBTA alerts page is the place to check any given stop on the day you ride.

The schedule calls for substantial completion in December 2026, with all new stations reopened and Fairbanks and Kent closed. The remaining punch-list work, including tree planting, is scheduled for spring 2027. On eastbound Beacon Street, the U-turn restriction at Hawes stays in place during construction. Brookline Public Works answers questions at 617-730-2177. The MBTA project team can be reached at 781-234-8641 or [email protected].

How far a home is from its nearest platform is part of what makes daily life on Beacon Street easy, and for some addresses near Fairbanks and Kent that distance is about to change. If you are weighing how the new stop map affects a home you own or are considering along the C branch, Amy Mizner is glad to walk through it with you. Contact Me.

Follow Us On Instagram